Hi GGTrader,
Are you aware WKT received the approvals for the tailings dam back on the 21st of March 2024,
What I find alarming, is you are claiming the required "Well Advanced" and "upgrading" yet 4 months have passed since WKT stated the following.
https://www.asx.com.au/asx/statistics/displayAnnouncement.do?display=pdf&idsId=02788039
These are not "Upgrades" they were required as part of the Tanzania laws and WKT design.
The question shareholders should be asking, is why after 4 months after obtaining the approvals/requirements to install the additional monitoring are these works yet to be completed.
- Forums
- ASX - By Stock
- WKT
- Ann: Development Progress - Lindi Jumbo Mine
Ann: Development Progress - Lindi Jumbo Mine, page-6514
-
- There are more pages in this discussion • 888 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add WKT (ASX) to my watchlist
(20min delay)
|
|||||
Last
9.8¢ |
Change
-0.001(1.01%) |
Mkt cap ! $65.78M |
Open | High | Low | Value | Volume |
10.5¢ | 10.5¢ | 9.8¢ | $27.16K | 260.8K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 125030 | 9.8¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
10.5¢ | 159466 | 4 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 125030 | 0.098 |
1 | 50000 | 0.097 |
2 | 25876 | 0.096 |
3 | 23528 | 0.095 |
2 | 21989 | 0.093 |
Price($) | Vol. | No. |
---|---|---|
0.105 | 159466 | 4 |
0.110 | 308578 | 7 |
0.115 | 100000 | 1 |
0.120 | 299902 | 6 |
0.125 | 355166 | 6 |
Last trade - 16.10pm 03/09/2024 (20 minute delay) ? |
Featured News
WKT (ASX) Chart |