I was not the one quoting a resource at 1% Cu eq , I was referring to cut off grade at 1% two different animals
Want to quote figures ?
They show vertical development of 2.8 kms in table 8.1 of the PFS for LOM .
I am guessing the mine goes down 800 meters , (dependent on portal location in pit) so a decline would be roughly 800/0.08 = around 10,000 meters long or 10kms .
They use a figure of 2.8kms ???? that would not even cover the distance of the main decline let alone any egress drive
Is that one of the reasons they used $104 million as there LOM sustaining cost for mine development which seems low to me in this case ?
I guess the DFS will clarify everything
- Forums
- ASX - By Stock
- NWC
- Ann: Highly Successful Reserve Upgrade Drilling Program Completed
NWC
new world resources limited
Add to My Watchlist
5.36%
!
5.9¢

Ann: Highly Successful Reserve Upgrade Drilling Program Completed, page-47
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
5.9¢ |
Change
0.003(5.36%) |
Mkt cap ! $200.1M |
Open | High | Low | Value | Volume |
5.8¢ | 5.9¢ | 5.8¢ | $602K | 10.36M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
3 | 2580000 | 5.8¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
6.0¢ | 1321624 | 8 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
3 | 2580000 | 0.058 |
11 | 6279216 | 0.057 |
10 | 6166691 | 0.056 |
8 | 13259837 | 0.055 |
5 | 1874300 | 0.054 |
Price($) | Vol. | No. |
---|---|---|
0.060 | 1321624 | 8 |
0.061 | 250000 | 1 |
0.062 | 1106006 | 5 |
0.063 | 2000000 | 1 |
0.065 | 255006 | 3 |
Last trade - 10.41am 23/06/2025 (20 minute delay) ? |
Featured News
NWC (ASX) Chart |