UNS 0.00% 0.5¢ unilife corporation

the final on bernhard opitz, page-5

  1. 3,088 Posts.
    lightbulb Created with Sketch. 48
    It's been well documented, original schedule was production by end of 2010, now it's been put-back to, installed Q1'11 with run-ups & qualifying culminating in first product delivery late Q2 or early H2.

    The whole Prefill line currently is in Factory Acceptance Testing(FAT) @Mikron in Colorado, this includes not only the Mikon section but the WFI and other sections.
    Next is Site Acceptance Testing @Unilife, once installed, Q2.

    No great drama a couple of months extra as long as they get it right!

    That's how I interpret things. DYOR.

    Why I asked the question was, we had no detailed updates throughout the year for the Mikon build then right at the end we are told of the new schedule???
    I was just wondering whether a head did roll because of the important change in scheduled dates?

    AS did mentioned in Sydney that the next new 150M line will only take 9mths to build, maybe it will share parts of the existing line when installed.
 