    O GTC61 As you said you were not deliberately making up quotes from me, I will be as genital as possible.

    On that bases, you must not have read the complete document because, as per the the below quote from the "Barruecopardo 2024 Ore Reserve Estimate" it includes updates and Year 1 started Jan 1 2024. They are now in year 2.

    So do you want to have another go on what the issues are and why production is only 50% of budget???
    With the grade falling away how much more needs to go thought the sorters just to maintain the current production???


    "10 Update for 2024 Mining
    Mine production has been on-going 1st of January 2024 until 31st of August 2024. The base MRE
    model being dated 31 December 2023, therefore models and stockpile estimates have been
    depleted for the interim activity in 2024, so as to correctly estimate the correct Ore Reserve
    remaining as of 31 August 2024.
    The phase position has been updated with the surface EXC_Agosto2024_TOTAL_3D.dtm ,
    corresponds to the August end of month topographic survey as shown in the Figure 10-1
    Figure 10-1 End of month surface, August 2024
    During this eight month of operations a total of 4.4Mt of material has been excavated according
    to the reserves block model (saloro_202310_res_rot_6x6x5.mdl) to produce 503kt of high-grade
    ore and 414kt of low-grade ore. A total of 0.9Mt of ore at an average grade of 0.18% that
    contains 162,752 mtu. The material moved during this period is summarized in In Table 10-1.
    The mine is slightly initiating the ramp-up to achieve the 1.45Mt of ore during 2024. As can be
    seen the mine is slightly down on the annual physical plan on a year-to-date basis by the end of
    May. However, this under achievement of plan is not considered material in terms of the LOM
    plan supporting this ORE. The monthly targets for the remainder of 2024 (corresponding to the
    Barruecopardo 2024 Ore Reserve Estimate
    10-2 | Barruecopardo W Mine Doc. No. SLO_ORE_24 1 0
    months from the month 9 to the month 12 of the year 1 of the LOM Plan) have been slightly
    increased to regain this deficient, such that the end of year position is achieved.
    "

    https://hotcopper.com.au/data/attachments/6834/6834707-fff49cae98077c5580ffd091325dbb32.jpg








 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
3.3¢
Change
-0.003(7.04%)
Mkt cap ! $93.78M
Open High Low Value Volume
3.6¢ 3.6¢ 3.2¢ $163.2K 4.779M

Buyers (Bids)

No. Vol. Price($)
1 29276 3.3¢
 

Sellers (Offers)

Price($) Vol. No.
3.4¢ 500000 1
View Market Depth
Last trade - 16.10pm 31/07/2025 (20 minute delay) ?
EQR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.