    Looks like we're nearing the final stage of the mitigation and testing project all going to plan.. Tier 1's could be onsite in three weeks!

    Long-term production flow testing of Orita 4 and injection testing of Orita 2: 03/08 – 04/07

    • This test enables samples to be collected and analyzed for the purpose of validating steady-state
    resource conditions over an extended period (temperature, pressure, mass flow rate, mineral
    concentrations, etc.).
    • Large sample containers (1,000-liter) will be filled and shipped to select equipment providers for in
    house testing.
    Recommended date-range for third party visitation/witnessing is 03/22 – 04/07
    • Equipment removal: 04/08 – 04/10, though can be delayed to accommodate additional
    visitation/witnessing as needed.
 