Half year report.
The next planned product delivery was scheduled for mid-2025 under terms of an existing sales contract. Due to the delay in
the CPP construction and commissioning schedule, Lance will not produce sufficient quantities of uranium to satisfy the mid
2025 delivery obligation of this contract. As the quantity of Lance sourced production remains subject to ramp-up, an onerous
contract provision of US$4.6 million has been recognised in the half-year financial statements. Depending on the outcome of
current negotiations with the counterparty regarding schedules and quantities, and finalisation of how the delivery will be met,
all or part of the provision may be reversed in the full year financial statements at 30 June 2025.
Where is rock chip George our CEO,..???
- Forums
- ASX - By Stock
- PEN
- Ann: Half Yearly Report and Accounts
PEN
peninsula energy limited
Add to My Watchlist
0.00%
!
62.0¢

Ann: Half Yearly Report and Accounts, page-25
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
62.0¢ |
Change
0.000(0.00%) |
Mkt cap ! $99.19M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
PEN (ASX) Chart |
Day chart unavailable
The Watchlist
P.HOTC
HotCopper
Frazer Bourchier, Director, President and CEO
Frazer Bourchier
Director, President and CEO
SPONSORED BY The Market Online