    Right so they're forecasting 9 months of detailed design. Does anyone know if any of that design programme has been started on? Or did it all go on hold?

    There's a few flaws in the relationship links here. You need detailed design completed then IFC before starting construction. IFC is usually another month at least after DD. IFC missing completely from this schedule. Its also showing construction starting month 6. DD not finished until month 9. Needs a bit of work.

    I'd estimate 12 months from re approval to starting earthworks if no detailed design has been started.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
14.5¢
Change
-0.005(3.33%)
Mkt cap ! $267.4M
Open High Low Value Volume
15.0¢ 15.3¢ 14.5¢ $556.3K 3.731M

Buyers (Bids)

No. Vol. Price($)
47 2700087 14.5¢
 

Sellers (Offers)

Price($) Vol. No.
15.0¢ 524354 7
View Market Depth
Last trade - 16.10pm 28/07/2025 (20 minute delay) ?
SVL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.