BRETTO, how can anyone at CDU supervise? What would be the point? The spec is defined. As soon as you make a minor change, the contract is void and if it doesn't work, as jumpstart says, the costs are all on CDU. The contractors will be ruthless on this.
Crudely put, the spec says that we put through 10T/hr of ore, and get 250kg copper concentrate at 80% copper out the other end, plus 99% recovery of native copper out the side. SS have quoted on that and designed accordingly. WM could do much, much worse than go surfing on the Gold Coast. Come back for all the photo opportunities when it is being commissioned.