1. Key Milestones Achieved
Commissioning & First Gold
Construction Progress
- First gold poured on 1 July 2025 — delivered on time and within 9 months of construction starting.
- Smooth transition from dry commissioning (testing systems) to wet commissioning (actual ore processing).
- Power station (4.8 MW) completed in May and integrated with both the plant and Andy Well underground.
2. Safety & ESG
- All major surface infrastructure delivered or near completion.
- Underground mining workshop at Andy Well to be completed in July ahead of mine development.
3. Operations
- Zero Lost Time Injuries (LTI) — LTIFR = 0.0.
- TRIFR at 3.3 — still relatively low for a mining project in early operations.
- Over 300,000 hours worked during construction without LTI.
- No significant environmental incidents — a strong ESG record for the quarter.
4. Growth & Exploration
- Open Pit:
- Ramp-up underway with a third mining fleet mobilised.
- Two new open pits (Turnberry Central & South) started; first ore from St Anne’s North mined.
- Ore stockpiles building steadily.
- Underground:
- Andy Well mine fully energised, ventilated, and ready for July 2025 development start.
- Owner-operator mining model established — expected to deliver long-term cost savings.
5. Financial Position
- Strong drilling results from Turnberry with standout intercepts:
- 10m @ 5.20g/t Au (incl. 2m @ 23.23g/t Au)
- Several 1m high-grade intercepts >10g/t Au.
- Results extend the Turnberry Central resource up-dip toward surface — likely to extend Stage 1 open pit and add shallow high-grade ounces to near-term production.
6. Corporate
- Cash: $56m at quarter-end.
- No debt (other than underground mining equipment finance).
- Capital Spend: $68.6m on Murchison development vs DFS estimate of $45.7m — overrun mainly due to:
- Accelerating underground mining (brought forward to 2025).
- Mobilising a third open pit fleet.
- Building extra infrastructure earlier than planned.
- Funding: $60m institutional placement completed to:
- Expand open pit mining.
- Accelerate drilling.
- Plan processing expansion beyond 600ktpa.
7. Strategic Outlook
- Leadership transition — Chris Davidson (ex-Chief Development Officer) now Chief Operating Officer to guide ramp-up into steady-state production.
8. Risks & Considerations
- Q3 CY2025:
- Ramp-up of processing plant.
- First underground ore from Andy Well.
- Continued open pit ore delivery.
- Ongoing exploration to add near-mine ounces.
- Medium Term:
- Potential processing capacity expansion.
- Increased ore blending flexibility from open pit + underground sources.
- Owner-operator model could drive operating cost reductions.
9. Overall Assessment
- Cost Overruns: Already +$22.9m vs DFS — although justified by accelerated production, investors will watch for ongoing discipline.
- Ramp-up Risk: Transition from construction to steady-state operations can reveal bottlenecks.
- Gold Price Sensitivity: No hedging means high exposure to spot gold prices — good for upside, but risky if prices soften.
- Labour Market: Recruitment largely completed, but maintaining skilled workforce in WA mining market remains a challenge.
This is a highly positive operational and strategic update:
The market will likely view this as a de-risking milestone — shifting Meeka from developer to producer status with strong near-term growth potential.
- Delivered first gold on schedule.
- Established both open pit and underground mining readiness.
- Strengthened balance sheet for accelerated growth.
- Early drilling success suggests scope for organic mine life extensions and grade improvements.
- Forums
- ASX - By Stock
- MEK
- In good position
MEK
meeka metals limited
Add to My Watchlist
14.8%
!
15.5¢

In good position
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
15.5¢ |
Change
0.020(14.8%) |
Mkt cap ! $451.9M |
Open | High | Low | Value | Volume |
14.0¢ | 15.5¢ | 14.0¢ | $3.382M | 22.47M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
6 | 2867000 | 15.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
15.5¢ | 3330045 | 38 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
5 | 2837000 | 0.150 |
9 | 1173795 | 0.145 |
15 | 2289933 | 0.140 |
60 | 4889008 | 0.135 |
38 | 2365028 | 0.130 |
Price($) | Vol. | No. |
---|---|---|
0.155 | 2531851 | 30 |
0.160 | 3438129 | 23 |
0.165 | 2022249 | 19 |
0.170 | 845675 | 13 |
0.175 | 1126019 | 4 |
Last trade - 16.10pm 08/08/2025 (20 minute delay) ? |
Featured News
MEK (ASX) Chart |