I'm guessing that while Pybar continues building the declines to lower levels it's about the right time to begin a drive into the ore body, maybe they began doing that a few days ago. The drive length required is probably about 150 metres (just a guess) and drive size will be about 3 x 3 metres and for a 24/7 activity then 6 to 8 metres per day is another reasonable guess. I'm also thinking that CGT is usually ahead of schedule for all their development activities and that driving into the ore body will be another example of getting ahead of schedule.