MNS 0.00% 4.2¢ magnis energy technologies ltd

$1 by EOY, page-11

  1. 1,109 Posts.
    lightbulb Created with Sketch. 1324
    At 17.5% complete they hadn't finished clearing out the building which was expected to take more than a week and be completed by August 16.

    30th of August, clear out was complete and needed to provide critical information for Romball to carry out detailed engineering design work. 23%complete.

    20 Oct.

    Hole in the wall complete. Still an empty building. Still working on design work with Romboll. 33% complete.

    https://hotcopper.com.au/data/attachments/3783/3783681-596edf6845cdea748385f303d48143e6.jpg
    https://hotcopper.com.au/data/attachments/3783/3783679-3dfb726c7ae1c47b792a485300a1b662.jpg

    Didnt Frank say look put for an update in a two weeks? Quite some time ago.

    Anyway, next update at 60% less than 1 month after still having an empty building. Semi prodiction in less than 2 months.

    sounds legit.


 
watchlist Created with Sketch. Add MNS (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.