don't want to come off as a pessimist, am just trying to be a realist
in response to your previous query, it's going to take maybe 3-6 weeks to get a completion done properly, but they still need to tie it in.
I seem to recall they have all the approvals for the pipeline, and that would likely take somewhere between 3-6 months if none of the FEED work has been done already...it would likely need some cap raising.
The Tipperary 18X (now Santos Fairview lease) was an example of a one well-pipeline..similar length to a Lease Area Custody Transfer point..
pipeline costs are about $0.5m per kilometre, depending on pressure rating.