From the last ann on the 17th .... drill rig has been mobilised to well 138 and is expected to spud later in the week. Looking at the schedule (if i read it right) drilling from day 1 to day 4 (up to 350M) then run surface and cement, nipple up and test - stage to be completed by day 8. That's makes it today/tom?
Drilling then immediately continues for another week until they get to 1050m. etc etc . program for well 138 done in 29 days, give or take a week.
I'd guess an update tomorrow then if they stick to their "weekly updates during drilling programs" mantra.