Just thinking out aloud, if its taken seven months to complete roughly 55% of the plant refurbishment and by years end we,ve roughly 75% to 80% complete. 100% would take us to at least end of janurary,Take away Xmas holidays then were looking mid to late feb. Three months comishioning APG time. I guess we are going to start making an income beginnig of the third Quarter. Can,t wait.
- Forums
- ASX - By Stock
- %
Just thinking out aloud, if its taken seven months to complete...
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
TG1
TechGen Metals kicks off airborne geophys survey at Sally Downs copper play – a first for the permit
AVH
Avita boosts skin restoration product portfolio with 'dermal matrix' – a kind of next-level gauze made of fake skin