    Moosey,

    the following information (contained in the December 2010 Half Yearly Report) and listed here for each of EWC's major current and proposed projects, may be useful as a benchmark in respect of whether EWC has embarked on a 'can do' philosophy.

    Sengkang Power Station
    PPA: until 2022
    Commercial operation of 60MW gas turbine: September 2011
    Commercial operation of 60MW steam turbine: September 2012
    Cost: 60MW gas turbine plus 60MW steam turbine: US$160million
    Financed by Standard Chartered and Mizuho Bank

    Sengkang LNG Facility
    Commercial operation of 1mtpa LNG: 18 months following BPMigas POD approval
    Commercial operation of additional 2x0.5mtpa: at 21 months and then 24 months respectively following BPMigas approval.
    Cost: 2mtpa modular trains: US$350million
    Financed by non-recourse project finance (via Standard Chartered and Mizuho Bank) plus 2008 capital raising.

    PNG LNG Project
    Commercial operation 2mtpa LNG: end of 2013
    Cost: 2mtpa LNG plant: US$550million (2010 Annual Report, page 43)
    Cost: 2mtpa modular trains plus 150MW captive power station: US$900million
    Capital costs per metric tonne of LNG production: US$455
    Proposed to be financed by equity and debt finance (leading banks and gas industry specialist (2010 Annual Report, page 43)).

    LNG Hub Pagbilao
    Commercial operation of phase 1: 2012/13
    Cost: Phase 1: 130,000m3 storage tank: US$100million
    Cost: Phase 2: 130,000m3 storage tank: US$70million
    Cost: Phase 3: 2x150MW CCGT power station:
    Proposed to be financed by co-investment by financiers and industrialists in Philippines.

    Abbot Point
    Commercial operation: 24 months following approval of LNG facility location.
    Cost: 1mtpa LNG plant: US$250million
    Cost: 350km pipeline: US$388million
    Cost: 550km pipeline to Gilmore/Eromanga: US$862million
    Proposed to be financed by leading banks and gas industry specialists to co-invest and to provide project debt finance.

    Modular LNG Trains
    Cost per 0.5mtpa: including all support facilities (but excluding primary gas processing plant at gas field and power generation (via grid supply or captive power plant)): US$125-150million
 
watchlist Created with Sketch. Add EWC (ASX) to my watchlist
(20min delay)
Last
0.9¢
Change
-0.001(10.0%)
Mkt cap ! $27.71M
Open High Low Value Volume
1.1¢ 1.1¢ 0.9¢ $24.64K 2.365M

Buyers (Bids)

No. Vol. Price($)
4 1859285 0.9¢
 

Sellers (Offers)

Price($) Vol. No.
1.2¢ 288000 1
View Market Depth
Last trade - 16.10pm 04/10/2024 (20 minute delay) ?
EWC (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.