ASX ANNOUNCEMENT 24 SEPTEMBER 2008Cooper Basin Project...

  1. 184 Posts.
    ASX ANNOUNCEMENT 24 SEPTEMBER 2008
    Cooper Basin Project Update
    Purchase of Second Heavy Duty Drilling Rig
    Geodynamics is pleased to announce that a contract for the construction and supply
    of a second heavy duty drilling rig has been signed with National Oilwell Varco
    (NOV); a worldwide leader in the design, manufacture and sale of oil and gas drilling
    systems and components.
    This follows an extensive competitive international bidding process, based on a
    detailed technical and functional specification. The new rig will form part of the
    assets of the Geodynamics/Origin Energy Joint Venture, and will be devoted to the
    development of the Cooper Basin geothermal tenements.
    The NOV rig pictured is similar to the newly contracted 2000 HP A.C., 15,000 PSI
    high pressure, high temperature deep geothermal drilling rig that Geodynamics has
    contracted to be built in Edmonton, Canada. The Rig will cost USD$38.3 million or
    AUD$45.4 million and the timeframe for construction, rig up and commissioning in
    Canada is 22 months.
    This new rig will have the capacity to drill to 6,000 metres, manage higher wellhead
    pressures. It incorporates heavy duty rig hydraulics, along with a number of other
    features that make it better suited to the drilling of geothermal wells.
    This new rig, along with the existing Le Tourneau Lightning 100 rig provides the
    drilling resource capacity required for the proposed 50MW power station.
    Jolokia 1 completed to 4,911m
    Geodynamics is pleased to advise that Jolokia 1 has been successfully completed to
    a depth of 4,911m, with the rig being released on 21 September 2008. Whilst just
    short of the targeted depth of 5,000 metres, the company took advantage of a bit
    change to proceed with planned temperature and structural logging of the well using
    “state of the art” logging equipment especially brought into the country from the Gulf
    of Mexico. The results of this logging analysis will provide the company with valuable
    temperature and fracture information.
    Rig 100 will be mobilised to the Savina 1 site in the coming month. Savina 1 is
    located approximately 10km WSW of Jolokia 1 and 19km W of Habanero 3.
    Whilst only accessing one flowing fracture 100m below the top of the granite in
    Jolokia 1, there were many instances of drill gas peaks and abnormal bit behaviour
    (known as drilling breaks) whilst drilling in the granite. These instances are
    analogous to those observed at Habanero 1, prior to stimulation and ultimate fracture
    flow.
    Jolokia 1 will remain suspended for approximately 6 months while drilling Savina 1,
    after which Rig 100 will return to the Jolokia site. At that time the company expects to
    - 2 -
    undertake further evaluation of the well and implement a technical solution to allow
    multi fracture stimulation. This technical solution is being developed with the
    assistance of many parties including our JV partner Origin Energy.
    Closed Loop Flow Test Update
    Since the last update, the circulation pump supplier, Schlumberger, have engaged
    their global technical research and development organisation who are working
    towards having the pump upgraded and returned to service in 8 weeks. This
    program of works and timeframe has increased from the originally stated 3 weeks
    following detailed engineering investigations into the unique operating conditions
    encountered during the initial operations. Schlumberger have committed to providing
    a product of the highest possible quality and working together with Geodynamics to
    meet our goals.
    During these initial test programs, all parts of the geothermal operating system are
    rigorously tested and refined to enable reliable operations during the commercial
    phase.
    Geodynamics is working with Schlumberger to expedite the delivery schedule and
    assures shareholders that the company is doing its utmost to resume the closed loop
    flow test as soon as possible.
    The final product will be an application specific, first of its kind, system for the
    geothermal industry.
    As previously advised, the flow test is scheduled to run continuously for a period of
    six weeks. Upon completion of this test, the results will be subject to a period of
    external review and validation. A successful validation will mark the completion of
    Stage One of the Company’s business plan i.e. ‘Proof of Concept’.
    For further information please check our website (www.geodynamics.com.au) or
    contact Mr Gerry Grove-White or Mr Paul Frederiks on + 61 7 3721 7500.
    Gerry Grove-White
    Managing Director
    Participants in the Innamincka Joint Venture are:
    Geodynamics (Operator) – 70%
    Origin Energy Geothermal Pty Ltd* – 30%
    *A wholly owned subsidiary of Origin Energy Limited (ASX: ORG)
    - 3 -
    National Oil Varco 2000 HP AC drilling rig similar to
    the customised rig Geodynamics has ordered.
 
watchlist Created with Sketch. Add RNE (ASX) to my watchlist
(20min delay)
Last
0.6¢
Change
0.001(20.0%)
Mkt cap ! $4.357M
Open High Low Value Volume
0.5¢ 0.6¢ 0.4¢ $4.406K 856.7K

Buyers (Bids)

No. Vol. Price($)
14 5274884 0.4¢
 

Sellers (Offers)

Price($) Vol. No.
0.6¢ 6058246 9
View Market Depth
Last trade - 16.10pm 28/06/2024 (20 minute delay) ?
RNE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.