    Abadi Coal Project Update

    Coal FE Resources Limited (ASX:CES) today announced results from drilling at the Abadi project in Selo Lai
    Area, Muara Badak District, East Kalimantan, Indonesia.
    The twenty six holes have been drilled within a 300 hectare block. The location of the drill holes can be found
    in Figure 1. Of the 26 drill holes, total depths ranged from 28 – 97.5 metres. Total drilling comprised 1,811
    metres. From the drill holes there are 6 main coal seams; Seam A (A and A2), Seam B, Seam C, Seam D (D,
    D1 and D2), seam E and seam F with thicknesses of 0.38 – 6.99 metres.
    Figure 1: Drillhole Location
    Drilling results indicate a significant step towards Coal FE achieving the Board’s target of proving an economic
    resource. Twenty coal samples were analysed with dry basic analysis (adb), the range of coal quality can be
    seen in the table below:
    Table 1: Coal Quality Analysis Results
    Sample Code Total
    Moisture
    (%)
    (ar)
    Inherent
    Moisture
    (%)
    (adb)
    Ash
    Content
    (%)
    (adb)
    Volatile
    Matter
    (%)
    (adb)
    Fixed
    Carbon
    (%)
    (adb)
    Total
    Sulphur
    (%)
    (adb)
    Gross
    Calorific
    Value
    (Kcal/Kgr)
    (adb)
    BH-10,A1 Seam A 44.2 14.6 8.8 42.5 34.1 1.45 5057
    BH-10,A2 Seam A 43.7 16.3 9.2 44.3 30.2 0.44 4840
    BH-10,A3 Seam A 46.3 18.1 3.5 33.9 44.5 0.36 5213
    BH-10,A4 Seam A 43 18.9 9.5 42 29.6 0.28 4808
    Average 44.3 16.98 7.75 40.7 34.6 0.63 4979.5
    BH-07a,
    A1
    Seam
    A1
    45.1 23 3.2 41.4 32.4 0.84 5213
    Average 45.1 23 3.2 41.4 32.4 0.84 5213
    BH-08,A2 Seam
    A2
    42.8 15.2 11.3 40.2 33.3 1.56 4808
    Average 42.8 15.2 11.3 40.2 33.3 1.56 4808
    BH-03,B1 Seam B 47.25 15.6 6.2 42.4 35.8 0.27 5020
    BH-03,B2 Seam B 47.81 15.38 3.7 45.06 35.86 0.15 5037
    BH-03,B3 Seam B 46.42 14.86 4.9 44.53 35.71 0.16 5207
    BH-03,B4 Seam B 47.35 14.52 2.96 44.34 38.18 0.13 5212
    BH-03,B5 Seam B 46.81 14.4 3.92 44.5 32.28 0.14 5214
    BH-03,B6 Seam B 45.63 13.12 2.36 47.71 36.81 0.12 5616
    BH-03,B7 Seam B 44.4 12.68 3.79 50.16 33.37 0.18 5767
    Average 46.52 14.37 3.98 45.53 35.43 0.16 5296,14
    BH-04, C Seam C 44.4 16 11.2 41.4 31.4 0.27 5017
    Average 44.4 16 11.2 41.4 31.4 0.27 5017
    BH-01, D1 Seam D 46.5 17.6 1.6 45.5 35.3 0.47 4825
    BH-01, D2 Seam D 45.2 17.2 7.4 39.8 35.6 0.36 4844
    Average 45.85 17.4 4.5 42.65 35.45 0.415 4834,5
    BH-12, B1 Seam E 35.1 15.5 5.4 45.9 33.2 1.21 5394
    BH-12, B2 Seam E 44.6 15.7 5.2 44.6 34.5 0.91 4772
    Average 39.85 15.6 5.3 45.25 33.85 1.06 5083
    BH-16, C1 Seam F 43.8 17.2 7.5 40.7 34.6 0.46 5353
    BH-16, C2 Seam F 41.8 15.7 13.2 39.6 31.5 0.33 5294
    Average 42.8 16.45 10.35 40.15 33.05 0.395 5323.5
    From the results of 20 samples the average quality is:
    Table 2: Average Coal Quality Analysis Results
    Analysis Unit Basis Range
    Total Moisture % wt Ar 35.1 – 47.81
    Inherent Moisture % wt Adb 14.6 – 23
    Ash % wt Adb 1.6 – 13.2
    Volatile Matter % wt Adb 33.9 – 50.16
    Fixed Carbon % wt Adb 29.6 – 44.5
    Total Sulphur % wt Adb 0.12 – 1.56
    Calorific Value Cal/g Adb 4754 – 5767
    One of the drivers of the drill program is to detail and prove the Abadi project to meet relevant JORC measured
    resource requirements. Work on a JORC compliant resource estimate is in progress by our consultants,
    Ravensgate and should be completed in May 2008.
    Julian Chang
    Executive Director
    The information in this report that relates to Exploration Results or Mineral Resources is based on information compiled by Ms Liesl Kemp,
    a Non Executive Director of Coal FE Resources Limited, who is a Member of the Australasian Institute of Mining and Metallurgy. She has
    sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity undertaken
    to qualify as a Competent Persons as defined in the 2004 Edition of the “Australian Code for Reporting of Mineral Resources and Ore
    Reserves”. Ms Kemp consents to the inclusion in this report of the matters based on information in the form and context in which it
    appears.
    Principal Office
    1/76 Canning Highway, Victoria Park, WA 6100. Phone: +61 8 9470 9156 Fax: +61 8 9470 9157 Website: www.coalferesources.com
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.