It's time for a Market Reality Check !
As all current BLR holders would know, this Announcement regarding Ablation Unit Construction was released on January 22nd 2013.
" Construction of an initial semi-commercial scale Ablation processing plant advancing well and scheduled for completion in April 2013. "
That being the case one would tend to suggest that Construction should be completed as per previous Company announcement, by the end of April
( Total Construction period being approximately give or take 14 Weeks )
From Tues Jan 22 - to current Today, Friday March 8 Construction period is
( nearing 7 Weeks ).
Got That !
So lets say construction had already begun prior to announcement
(conservatively 1 Week)
That puts the first Unit in the current construction stage of approx, ( 8+ Weeks )
Got That !
With the above assumption one would assume that we are nearing 60% completion of the initial semi-commercial scale Ablation Recovery Unit.
Got That !
Putting pictures into words, current construction progress I would assume, would currently look similar to this :)
near 60% Complete
P.S. My musings only DYOR !
Cheers :)
It was good to see a slight U3O8 March 2013 futures increase overnight up 25c to $42.40P/Lb
.
.
- Forums
- ASX - By Stock
- BLR
- ablation recovery unit progress update
ablation recovery unit progress update
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add BLR (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
LU7
LITHIUM UNIVERSE LIMITED
Alex Hanly, CEO
Alex Hanly
CEO
Previous Video
Next Video
SPONSORED BY The Market Online