    MEK -- Project Permitting
    The Company is confident, based on the work completed to date and the information available, that approvals required for development will be granted in the June quarter 2024.The following key permits will be required:
    DMIRS:
    ✓ Mining Proposal (MP) and Mine Closure Plan (MCP) – application
    submitted December 2023. Approval expected June quarter 2024.
    ✓ Native Vegetation Clearing Permit (NVCP) – received.
    DWER:
    ✓ Works Approval / Prescribed Premise Licence (processing operations,
    mine dewatering, waste water treatment, chemical storage, crushing
    of rock and putrescible landfill) – permit in place.
    ✓ Works Approval / Prescribed Premise Licence (open pit mine
    dewatering and landfill) – application submitted December 2023.
    Approval expected June quarter 2024
    Worth watching now, imo.
 