    Nothing particularly new or shocking. All resolutions were passed. Presentation given at the end of the meeting.

    Still quoting $400USD

    From the presentation:

    Some changes to the timetable. Scoping study extended to March next year to take in DSO option.

    CAPEX/OPEX numbers due in December will be for the full 3MT pa, benification, etc option and won't include DSO.

    If DSO proves to be a viable option they could be shipping by the end of 2009

    Stage 2 environmental approval looks to be a formality with no endangered plants / animals etc in the area.

    From questions from the floor:

    Held financing talks in North America a few months ago with a view to returning early next year. While they used rough cap/opex numbers at the time they were told that it was "do-able"

    Current Darwin port capacity is obviously limited. The port expansion is a must for the company. Worst case if the NT govt haven't come through with the goods they're exploring building the facilities themselves. (compensation / royalty relief etc) They've also explored the option of sending the ore south (port not ready, de-railment, etc)

    Tennant creek hub third party is waiting on pastoral lease approvals

    Directors and "friendly parties" hold roughly 35% of shares and are not interested in a take over (Interestingly as soon as the question was asked Ted Ellyard said "BHP". Can only assume jokingly...)

    More to follow when i remember it.....
 