Updated Build 1, as the latest video has a little new info.Build...

  1. 1,530 Posts.
    lightbulb Created with Sketch. 329
    Updated Build 1, as the latest video has a little new info.

    Build 5 (3rd house [2nd house in Wellard])
    Location: 2 doors along from last build, so perhaps 9? or 17? Coracina Vista, Wellard 6170
    Builders: Inspired Homes? on FBR-owned land, using HX2
    Materials: 4343 concrete blocks
    Weather: Worked in some heavy rain
    Completed: 29 Sept 2021 to 3 Oct 2021 ? (29 laying hours, so 149 blocks/laying hour)
    Details: 4 bedroom, 2 bathroom house. dble leaf cavity wall. Small tech issue with motor in boom. Total distance travelled by layhead: 8.2km. Wall area: 354.43sqm.
    Special: double crew - training new operators
    Income:

    ===========================================================================

    Build 4 (2nd house [1st in Wellard])

    Location: lot 861, 13 Coracina Vista, Wellard 6170 (little south of Perth)
    Builders: Dale Alcock on FBR-owned land, using HX2
    Materials: 3456 concrete blocks (230mm high) (~21,780 SBE).
    Weather: Waited for bad weather to pass then built in beaut weather.
    Completed: 2 Aug, 2021 to 6 Aug 2021 (4 and half days, 29 laying hours, so 119 blocks/laying hour)
    Details: Lot is 374 sq m. 4 bedroom, 2 bathroom house. dble leaf cavity wall
    Special: down to 1 operator in control van and 2 people on site ("could get away with one"). Site person does things like loading HX with blocks using telehandler, installing brick ties. Next build to be next door once slab cured.
    Income: ? The price paid for 3 of the 5 bare lots was $555,000

    ===========================================================================

    Build 3 (2nd non-residential/commercial): childcare centre
    Location: Amberton Beach, near Eglinton, northern Perth
    Builders: Dale Alcock, using HX2
    Materials: 8,670 concrete blocks (390mm x 90mm x 230mm) (36,500 SBE). Lintels (up to 4.8m long) made by FBR. Termimesh on slab; waterproof damp course flashing on first course and over lintels (coastal environment). Internally lined with 10mm plasterboard; externally lined with 10mm Acratex Texture Coat.
    Weather: worked in some very heavy rain and strong winds
    Completed: 5 June, 2021. 16 build days (57 laying hours - which calculates to 152 blocks/laying hour)
    Details: >60m long slab, big build (size of about 5 houses), walls up to 4.8m high. dble leaf cavity wall. Water not connected to site. Some minor mechanical issues.
    Special: 25 windows, many small ones; HX had to build from 5 different positions; FBR made the lintels
    Income: prevailing commercial rate; $91,800 revenue

    ==============================================================================

    Build 2: community centre (first commercial structure)
    Location: Byford, WA; 40km south of Perth; cnr Balawarra and Kardan Blvd
    Builders: Archistruct, using HX2 and WaaS
    Materials: 4,413 concrete blocks (390mm x 230mm high x 90mm thick) or ~20,300 SBE

    Weather: sunny, cloudy, hail, high winds, heavy rain
    Completed: Tues 1 Sept - Tues 8 Sept, 2020 (HX returned to HQ for weekend). 25 laying hours (so 176.5 blocks/laying hour). Tenanted by real estate co and a cafe Feb 2021.
    Details: dble leaf cavity wall, step-down course below the slab; av lay speed 174 blocks/hr (800 SBEs/hr); top speed 228 blocks/hr; 15 courses high (~1.5 storeys); brick ties manually installed. Rendered finish.
    Special: 1st non-residential structure, new adhesive application system. Roof trusses made in advance according to CAD model.
    Income: prevailing commercial rate

    ==================================================================================


    Build 1: Display home

    Location: 31 Elderberry Drive, Dayton 6055, WA; site bordered by 7 occupied homes
    Builders: Archistruct Builders and Designers; using HX2
    Materials: 2991 blocks (390 x 230mm x 90mm; 13,759 SBE)

    Weather: some light rain, also dark/low light
    Completed: 8 July - 11 July, 2020 (3 and a half days; HX deployed 7 July, started building 8th); Open home 24 April 2021 postponed to 1 May following lockdown.
    Details: 4 bedroom, 2 bathroom residential home; 11 courses. Single leaf wall. Average lay speed when running 146 blocks/hr (671 SBEs/hr); peak 228 blocks/hr (1,049 SBEs/hr). Slab 219sqm. Entire structure completed in 20.5 laying hours. Less than 0.1% wastage of blocks.
    Special: First real build; roof trusses and prefab kitchen ordered from 3D TAD; Mike interviewed by Channel 9 News
    Income: ? House sold for $532,000 in May 2021
 
watchlist Created with Sketch. Add FBR (ASX) to my watchlist
(20min delay)
Last
4.6¢
Change
0.001(2.22%)
Mkt cap ! $221.9M
Open High Low Value Volume
4.6¢ 4.9¢ 4.5¢ $387.1K 8.299M

Buyers (Bids)

No. Vol. Price($)
4 315279 4.6¢
 

Sellers (Offers)

Price($) Vol. No.
4.7¢ 221109 2
View Market Depth
Last trade - 16.10pm 04/10/2024 (20 minute delay) ?
FBR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.