Round up:
1) 10% OPEX reduction before by-product credit
2) Gypsum by-product additional credit
3) SOP (as announced in scoping study - 54K tpa)
4) Boron main game
5) Li potential
Time Line:
1) 2H 2018 - DFS to be ready
2) Air permit - required for construction - to be lodged in the next few weeks (takes few months to get approved)
3) Water permit - required for production - to lodged by Q4 2018 (takes few months to 18mths worse case scenario to get approved)
4) All ready to proceed with construction by Mid CY2019
Should see our first product some time in 2020?
ABR Price at posting:
29.5¢ Sentiment: Hold Disclosure: Held