Ann: ADDRESS: TPW: TrustPower Annual Meeting Chai

  1. lightbulb Created with Sketch. 2
    • Release Date: 03/08/12 16:30
    • Summary: ADDRESS: TPW: TrustPower Annual Meeting Chairman's Address
    • Price Sensitive: No
    • Download Document  11.28KB
    					
    
    TPW
    03/08/2012 14:30
    ADDRESS
    
    REL: 1430 HRS TrustPower Limited
    
    ADDRESS: TPW: TrustPower Annual Meeting Chairman's Address
    
    Chairman's Address - Annual Meeting 3 August 2012
    Welcome
    I would now like to introduce my fellow directors to you.  All have
    significant relevant experience, qualifications and skills.  The focus of
    your board is on understanding and looking after the risks inherent in our
    business, and also positioning for the major decisions we see coming up.  By
    decisions coming up i do not just mean dealing with our current business - I
    mean a lot more than that - I mean being able to contribute to strategy and
    support and encourage management to pursue opportunity.   Our focus is on
    value and in our industry that means good positioning for the medium to long
    term.
    If you look across the Director team you will see experience in major
    engineering projects, experience in the evolution of water markets and
    irrigation economics, experience in IT and in customer facing systems in both
    banking and telecoms, and you will also see quite deep electricity sector
    experience.
    First, I would like to introduce Mr Michael Cooney who will no doubt be
    familiar to many of you.
    - Michael is Chairman and a Trustee of the Tauranga Energy Consumer Trust.
    - Michael holds a law degree and is a consultant to the local law firm
    Cooney, Lees and Morgan, and previously he was a longstanding partner of the
    firm.
    Next is Mr Marko Bogoievski.
    - Marko is a Chartered Accountant and holds an MBA from Harvard University.
    - Marko is Chief Executive of Infratil Limited
    Next is Mr Geoff Swier.
    - Geoff holds a Masters of Commerce degree.  He has over 20 years experience
    in micro economic reform in Australia and New Zealand focusing on the
    establishment of competitive energy markets and privatisation as well as the
    development of water industries in Australasia and Asia.
    - Geoff was previously an associate member of the Australian Competition and
    Consumer Commission and a member of the Australian Energy Regulator.
    Next to Geoff is Sam Knowles.
    - Sam has considerable experience in the banking and insurance industry
    specialising in areas including strategic planning, retail services,
    marketing and business development. Sam was previously Chief Executive of
    Kiwibank and is now a professional director.
    Next to Sam is Richard Aitken.
    o Richard is Executive Chairman of the Beca Group.
    o Richard holds an Engineering Honours degree and a Masters of Engineering
    Science degree from Sydney University. Richard has extensive engineering
    project management experience in major power and water infrastructure
    projects.
    o He also has a lot of experience in contractual matters pertaining to these
    major projects.
    I would also like to introduce your Chief Executive, Vince Hawksworth and
    also your Chief Financial Officer Robert Farron and also offer a welcome to
    the TrustPower senior management team most of who are with us today.
    We will hear more from Vince shortly.
    Now to return to the more formal business of reviewing the 2012 financial
    year.
    The Group delivered a strong increase in underlying earnings after tax of
    $135.5 million up 16% on prior year.  Your Directors consider this was a very
    good result given the intense retail competition and a volatile wholesale
    market in the second half of the financial year.
    TrustPower has paid dividends of 40 cents per share for the 2012 Financial
    Year representing a 2.5% increase over prior year.
    Debt (including subordinated bonds) to debt plus equity decreased to 33% at
    year-end down from 36% the previous year as a result of lower borrowing
    levels and the independent revaluation of generation assets which resulted in
    an uplift in generation asset values of just under $200 million.
    TrustPower has achieved a significant milestone with the financial close of
    its Australian wind project -  Snowtown II.
    This is the result of four to five years of strategic intent - an intent
    built off recognising that New Zealand is a small market with modest load
    growth and that TrustPower's capabilities exceed its New Zealand
    opportunities.
    TrustPower also recognised that wind Power is the lowest cost means for
    Australia to reduce its dependence on coal.  Renewables policy in Australia
    is designed to see wind not only meet load growth but, when coupled with
    pricing carbon, this policy is designed to push the closure of the least
    efficient thermal plants.   Carbon prices alone would not achieve this.
    For Snowtown II, all key agreements and approvals required for the
    development have been entered into or secured. Foreign exchange hedging
    arrangements to cover Euro and USD currency exposure on the Project Capital
    expenditure have been completed at favourable rates and the expected total
    project cost (excluding capitalised interest) has reduced from A$465 million
    to A$439 or $A 1.6 million / MW.
    Snowtown Stage 2 represents a very attractive investment for TrustPower.   We
    have locked in lower than expected costs for the construction and we have
    secured a long term contract with a good counterparty for selling the wind
    energy at fixed but inflation proof prices.
    While no project is without risk, wind farms are at the low end of the scale
    and TrustPower is not new to wind farm development and has a good track
    record of contracting well and delivering well.  The expected cash flows to
    TrustPower post commissioning are strong.  The expected returns are
    exceptionally good for a such a low risk project and when you have a good
    project it is also good that it has some scale.
    TrustPower will fund the project via Australian dollar bank facilities
    provided by its relationship banks.  While these facilities will mature in
    late 2014, it is expected that a proportion of these facilities will be
    refinanced in the next 12 months with long term Australian dollar debt
    facilities.
    The additional debt required to fund Snowtown Stage 2 will significantly
    increase the Group's gearing (debt to debt plus equity) ratio.
    However, TrustPower anticipates that the gearing ratio will be comfortably
    within the upper limit of the Group's target gearing ratio range of 25-50%
    and that the Group will operate within its banking covenants during
    construction of Snowtown Stage 2 and after commissioning of the project.
    Your Directors are comfortable with these debt levels but we are also mindful
    that we wish to have firepower in the tank to be able to take other wind
    opportunities in Australia.  Thus we have positioned to allow a sell down of
    the southern part of the Project.  Such a sale realises the value of the
    strong returns from the project in the form of a development profit.
    TrustPower has ensured it has flexibility for this sell down to be pre
    construction, or at completion, or anytime thereafter.
    Directors are confident that modest growth in dividends can be maintained
    with a high proportion of imputation.
    Financial close of the Snowtown Stage 2 project is an important milestone for
    TrustPower in terms of its wind development aspirations in Australia.
    TrustPower holds development options over a further 1,280 MW of wind
    generation opportunities in South Australia, Victoria and New South Wales and
    is looking to advance development planning submissions for some of these
    opportunities over the next 12 months.
    Your Company continues to work hard at building a range of growth options in
    New Zealand and in Australia and we are positioning the balance sheet to
    support execution if and when we get excited about the shareholder value gain
    from that investment. Exclusively we have targeted low impact hydro
    developments and wind projects in locations with good wind resource, low
    connection costs and a high level of community acceptance.
    Your Company's approach is simple - to identify good sites for projects, to
    secure the consents and development rights and then to execute selectively
    when market conditions reflect that more energy is needed and when we can get
    good competitively priced contracts and warranties from suppliers.  Our aim
    is not to get bigger but to add shareholder value.  The Snowtown Stage 2 wind
    farm development is an excellent example of this focused approach to growth.
    
    On the retail side of the business it is very clear that the market remains
    very competitive and that customers have choices and can change their
    supplier if they are not happy with the service, or the price, or the
    corporate responsibility of their retailer.   Your company has never seen
    retail as a route to market for its generation schemes, it has always strived
    for service excellence, low costs to serve and relevance to its customers.
    TrustPower's retail business is performing well despite the fall in customer
    numbers in the context of the very competitive retail market.  The completion
    of the project to replace the Company's core customer and information systems
    has now established a strong foundation from which to improve product
    offerings and interaction with our customers.
     I also wish to comment more broadly on energy matters and climate change.
    In New Zealand, you could be forgiven for thinking that Climate Change had
    somehow gone away as a topical issue - certainly we are on a go slow.  This
    is in contrast to countries like the United Kingdom and Australia.
    Climate change skeptics are struggling with overwhelming evidence of human
    induced global warming - the scientific debate is no longer a debate.
    What is also clear globally is that to make a difference the electricity
    sector has to do more than its share as we don't have the technology to make
    big dents in transport just yet.   Europe and the United Kingdom and
    Australia have realised this.  In the United Kingdom the decision has been
    made to ensure that targets are automatically increased as renewables come on
    stream - this will force the closure of coal plants or the conversion of
    these plants to renewable fuels.  This is a very long term game with
    consistency in policy settings necessary for investment in capital intensive
    projects.   The GFC has not been allowed to divert the consistency of these
    signals, which are specific to renewable electricity and not linked to
    volatile and immature carbon markets.
    What have we done in New Zealand?   We have actually done a good job of
    getting a framework in place and improving the mechanics of CO2 pricing.
    Carbon pricing schemes sensibly link CO2 prices to international levels.
    however, international markets are immature and CO2 prices have collapsed in
    the last year or so as a result of the fall out following the GFC and the
    subsequent recessionary impacts on Europe.  Thus signals in New Zealand,
    which had already been halved by the transitional 'two for one' allocation
    are of little influence as we speak.   We have got it right with this
    international linkage but we are wrong to rely on this alone until
    international markets are more mature.  The approach must be pragmatic and
    realistic in respect to international developments but complementary measures
    are also needed.
    Electricity is typified by very long term capital assets - we are at risk of
    embedding a higher CO2 asset base if we don't have the right signals for
    renewables ahead of fossil fuels and at present we don't have those signals.
      Removing the 'two for one' allocation in electricity generation would help
    speed up the closure of inefficient polluting coal plant and also help avoid
    gas plant being built ahead of wind.
    
    I will now hand over to Vince for his presentation.
    Thank you
    End CA:00225633 For:TPW    Type:ADDRESS    Time:2012-08-03 14:30:46
    				
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.