Well Site Construction Completed and Rig
Mobilisation Commences for the Anshof
Exploration Well
Key points:
The construction of the Anshof well site has been completed in preparation for the drilling
of the Anshof Prospect in the ADX-AT-II license in Upper Austria (refer to figure 1).
The RED Drilling & Services GmbH (RED) E-220 rig commenced mobilisation to the
Anshof well site on the 13th of December 2021.
The first well that will be drilled from the Anshof well site will be from the Anshof-3 surface
location.
An overview of the Anshof Prospect is available in Appendix 1 at the end of this release.
It includes the results of an independent prospect review undertaken by RISC Advisory
Pty Ltd (“RISC”).
ADX announced a farmout to ASX listed Xstate Resources Limited to fund 40% of the
Anshof-3 well costs to earn a 20% participating interest in the Anshof Prospect. Refer to
ASX release dated 22 November 2021.
The Anshof-3 surface location is outside an area which requires additional approval by
the Forestry Authority. Drilling from this location has enabled the commencement of well
site construction to meet a rig slot available in December 2021.
ADX Energy Ltd (ASX Code: ADX) is pleased to advise that the construction of the Anshof well site
has been completed in preparation for the drilling of the Anshof prospect in the ADX-AT-II license in
Upper Austria. The completion of the Anshof well site has enabled the commencement of mobilisation
of RED Drilling & Services GmbH (RED) E-220 rig on the 13th of December 2021. The first Anshof
Prospect exploration well will be drilled from the Anshof-3 Well surface location. The Anshof-3 Well
surface location is outside an area requiring approval by the Austrian Forestry Authority. Drilling from
this location has enabled the commencement of well site construction to meet the drilling rig
availability during December 2021. ADX expects approval by the Forestry Authority for the two
additional surface locations for drilling by year end allowing follow up appraisal and development
drilling
- Forums
- ASX - By Stock
- XST
- Ann: ADX: Anshof Well Site Construction Underway - Drilling Dec.
Ann: ADX: Anshof Well Site Construction Underway - Drilling Dec., page-58
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add XST (ASX) to my watchlist
(20min delay)
|
|||||
Last
1.1¢ |
Change
0.000(0.00%) |
Mkt cap ! $3.537M |
Open | High | Low | Value | Volume |
1.1¢ | 1.1¢ | 1.1¢ | $191 | 17.34K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
3 | 495496 | 1.1¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
1.2¢ | 180521 | 3 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
3 | 495496 | 0.011 |
6 | 1895099 | 0.010 |
4 | 1242443 | 0.009 |
3 | 630123 | 0.008 |
1 | 200000 | 0.007 |
Price($) | Vol. | No. |
---|---|---|
0.012 | 180521 | 3 |
0.014 | 236000 | 4 |
0.015 | 1439235 | 4 |
0.016 | 500000 | 1 |
0.017 | 217500 | 2 |
Last trade - 10.37am 14/06/2024 (20 minute delay) ? |
Featured News
XST (ASX) Chart |