On Friday March 19th the workover / completion rig arrived on site.
Set-up of the power plant and support equipment for the rig was completed over the weekend and
completion work on the well commenced.
The targeted Benbrook sand was perforated from a depth of 6,455.5 6,460.5 feet.
Production tubing has been successfully run and sucker rods are scheduled to be installed tomorrow.
All 1.7 miles of right of way have been cleared and are now awaiting pipe installation.
PAD site construction for the tank battery, heater treater, and separation equipment has begun.
The saltwater disposal well has been tied back and is on schedule to be drilled out shortly.
- Forums
- ASX - By Stock
- AKK
- Ann: Armstrong Ellislie No1 update
Ann: Armstrong Ellislie No1 update , page-2
-
- There are more pages in this discussion • 17 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
STX
Strike hands $48.5M contract to Clarke Energy to produce 20x 4.5MW gas engines for Sth Erregulla
KAI
Pilbara Minerals buys land off Kairos part of its York gold project for $20M – and a 2% royalty on any PLS gold sales