On Friday March 19th the workover / completion rig arrived on site.
Set-up of the power plant and support equipment for the rig was completed over the weekend and
completion work on the well commenced.
The targeted Benbrook sand was perforated from a depth of 6,455.5 6,460.5 feet.
Production tubing has been successfully run and sucker rods are scheduled to be installed tomorrow.
All 1.7 miles of right of way have been cleared and are now awaiting pipe installation.
PAD site construction for the tank battery, heater treater, and separation equipment has begun.
The saltwater disposal well has been tied back and is on schedule to be drilled out shortly.