Regard drilling: Hole 1 finished on 14-Feb. Hole 2 finished on 25-Feb. So it takes about 11 days to complete a hole.
Roche Dure: plan to drill 21 DD holes. By mid March, 4 holes would have been completed, leaving 17 holes to drill. Assuming drill #5 will not arrive until mid-Apr, we would have completed a further 11 holes (4 drills x 31 days / 11) by this time and leave 6 more holes to drill. This will take approx until the end of Apr to finish all 21 DD holes.
Carrier de L'est: plan to drill 26 DD holes. With 5 drills and average 11 days to finish a hole, it will takes about 57 days or end of Jun to finish all the 26 holes.
If one takes the plan RR holes into consideration, we probably won't finish the 20,000m drilling program some time in Q3-2018. However, this assumes that all holes are of equal depth.
I don't know what Klaus and Nigel plan are, but hope that they will have a staggering approach to get to JORC for Roche Dure first while still drilling Carrier de L'est and keep momentum.
- Forums
- ASX - By Stock
- AVZ
- Ann: AVZ hits 282.95m of spodumene bearing pegmatite at Manono
Ann: AVZ hits 282.95m of spodumene bearing pegmatite at Manono, page-86
-
-
- There are more pages in this discussion • 121 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add AVZ (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
I88
INFINI RESOURCES LIMITED
Charles Armstrong, CEO & Managing Director
Charles Armstrong
CEO & Managing Director
SPONSORED BY The Market Online