WTI $66.26 -24c, Brent $69.88 +21c, Diff -$3.62 +45c, NG $4.13 +7.6c, UKNG 221.43p -12.37p

Oil price

Last week WTI was down $2.49 and Brent fell $2.84 which was in line with the omicron panic and also that Opec+ left the decision re extra production hanging. Today crude is up about about $1.50 as there are some reports that omicron may be less hard hitting than other variants although it certainly is more contagious.

Also it looks like the nuclear talks are not going so well, the French have walked out and it seems that with Iran itself acknowledging that it is produced enriched uranium which is a deal breaker. The rig count was unchanged with oil units at 467 itself unlikely to jack up US domestic production.


Far

FAR Ltd (ASX: FAR) advises that the Bambo-1 well has drilled 3216m MDBRT (measured depth below the rotary table) of a total planned depth of 3450m MDBRT. Oil indications have been detected in rock cuttings and hydrocarbons have been interpreted across several intervals in the well from LWD data. Further wireline logging needs to be completed to confirm the finding.

Drilling operations were temporarily halted at the current depth after significant fluid losses were experienced. These fluid losses were stabilised in accordance with standard offshore operating procedures, and FAR is now planning to plug and side-track the well to continue drilling to the planned total depth. Prior to side-tracking and provided hole conditions remain stable, FAR is undertaking a wireline logging program in the current well bore.

FAR estimates that the cost to complete the well will increase from a total of US$51.4M to US$61.27M, an increase of US$9.87M or US$4.935M net to FAR. FAR forecasts a cash balance of US$37M after the completion of the well, inclusive of the increase in Bambo-1 well costs. The addition of the side-track program has extended the period of operations which is now expected to be completed by the end of December 2021.

The well has been designated a “tight hole” by FAR and JV partner Petronas and as such, no information related to depth or formation is likely to be provided during the drilling beyond what is required to meet ASX continuous disclosure obligations. Market participants should exercise care before transacting in FAR shares until such time as FAR, as Operator of the Joint Venture, makes formal ASX disclosures regarding well results.

FAR’s Managing Director, Cath Norman, said

“FAR is pleased with the experienced drilling team and contractors who have acted to quickly manage and adjust the Bambo-1 drilling program to suit the geological setting and best meet the objectives of the drilling program. FAR is well placed to achieve these objectives through the side-tracked well and in particular drilling through the as yet undrilled Soloo Deep prospect. We are encouraged by the presence of oil in potential reservoirs and look
forward to completing the well in the coming weeks.”

It’s a bit early to tell anything conclusive and the company are wise to be cautioning about trading during a designated tight hole but my spies who have been very positive about this from the start are already convinced there is something down there worth going after so watch this space…