    22 out of 82 planned holes completed.

    Drilling started on September 8th, which was 2 weeks ago.

    Assuming they work 6 days per week, it is almost 2 holes per day.

    60 holes remaining, about 30 - 40 days until drilling is completed.

    No hype in this announcement, but the photos of those cores indeed look "very encouraging".

    It's interesting that the samples are going to ALS in Perth.

    I would have thought WAI would be handling that as they will also be doing metallurgical studies.

    Probably best they come here, especially if we pay in AUD given the way the AUD is collapsing.

    2 months, 1 week and 4 days until the end of November.
 