KLL 0.00% $7.28 kalium lakes limited

Ann: Beyondie SOP Project - Operations Update, page-37

  1. 2,703 Posts.
    lightbulb Created with Sketch. 16
    I may been reading this wrongly , But the way I take it is that the RAMP UP is starting in October not the first production .
    this latest announcement states
    Commencement of production ramp-up remains on track for October 2021
    But when you go back to the investor presentation on the 23/8
    Production Imminent
    2
    3
    4
    5
     Beyondie SOP Project is substantially de-risked with first production on target for
    September and commercial production ramp-up to commence in October 2021
     Construction near completion, commissioning commenced
     100% of expanded production committed to offtake with K+S

    So my way of thinking is this latest announcement is only talking about the ramp up
 
watchlist Created with Sketch. Add KLL (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.