    But they are literally canning further work on the DFS:

    2 BHCP – Review
    The technical work packages defining the BHCP Definitive Feasibility Study (DFS) are nearing completion however, given current
    battery minerals pricing, particularly cobalt metal trading at US$12–14/lb, as well as the current inflated capital cost environment,
    the BHCP (in its current form) is presently unlikely to attract project financing.
    Rather than deliver a DFS that effectively “sits on the shelf”, waiting for a future upturn in the macro environment, the COB Board
    has paused completion of the DFS (in its current form) and requested management to undertake a Review to assess the viability of
    a condensed higher margin project. The Review will likely make substantial use of the extensive library of technical studies, reports
    and other work undertaken for the DFS

 
watchlist Created with Sketch. Add COB (ASX) to my watchlist
(20min delay)
Last
8.4¢
Change
0.000(0.00%)
Mkt cap ! $35.42M
Open High Low Value Volume
8.4¢ 8.6¢ 8.2¢ $76.90K 913.9K

Buyers (Bids)

No. Vol. Price($)
1 196580 8.2¢
 

Sellers (Offers)

Price($) Vol. No.
8.5¢ 193756 2
View Market Depth
Last trade - 15.59pm 07/06/2024 (20 minute delay) ?
Last
8.4¢
  Change
0.000 ( 1.20 %)
Open High Low Volume
8.3¢ 8.6¢ 8.2¢ 398545
Last updated 15.57pm 07/06/2024 ?
COB (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.