Looks like ENI has a different tact for B#2 unlike MEO's B#1 which was drilled as a 12.25" hole to TD of 3286m.
ENI will case above the Flamingo sands at B2, around 3130-3149m mark & then drill ~220m of the 8.5" dia hole till TD of 3286m.
Basically another week/10 days to drill 1764m to nxt csg point (from 1376 to 3140m), then log that section b4 running 12.25" casing & cementing. So mid Nov, they should b in the Plover, on a trouble free basis & should TD by week-3 b4 logging the reservoir section.
Refer the WL log for B1 in my post# 9831465.