    Yep. adding 2 days for loading to the arrival date of the next two ships has us at 15 days.
    • Mine trucking started on 24th Dec
    • PanAfrican departed on 9th Feb (57 days)
    • Marinicki departed on the 24th Mar (43 days)
    • Ballard departed on the 24th April (4 or so days late due to cyclone)) - 30 days
    • Banasol departed 16th May (22 days)
    • YARRAWONGA depart on the ? 9th ? June (24 days)
    • DARYA MA depart? 24th ? June (15 days)

    Happy with that.
    I wonder what happens with that independent contractor and night shift. Will we see sub 15 days?
 
watchlist Created with Sketch. Add GWR (ASX) to my watchlist
(20min delay)
Last
8.0¢
Change
0.000(0.00%)
Mkt cap ! $25.69M
Open High Low Value Volume
8.0¢ 8.0¢ 8.0¢ $727 9.091K

Buyers (Bids)

No. Vol. Price($)
1 29999 8.0¢
 

Sellers (Offers)

Price($) Vol. No.
8.5¢ 200000 1
View Market Depth
Last trade - 10.04am 19/07/2024 (20 minute delay) ?
GWR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.