ARU 0.00% 19.5¢ arafura rare earths ltd

Ann: Capital Injection update , page-61

  1. 1,160 Posts.
    lightbulb Created with Sketch. 58
    "Once Arafura has made its production date available to the Market I will post it on HC for you all to read,that information is yet to be made available to the Market"

    mmartin

    There is adequate information from the Project Update to work out a production date:

    1. FID expected mid 2013 - this will obviously be delayed due to the inability to raise funds for the IPP but lets say FID is achieved by the end of 2013 + funding required for $1.9b - allow another 6 months to be generous.
    2. 36 months to construct (ref section 10.1)
    3. 10 quarters to ramp-up (ref section 10.1)

    Note detailed engineering cant be completed until the IPP has been built which delays order of long lead items.

    Therefore 6 years from the end of 2013 = start of 2020 to achieve nameplate capacity of 20,000 tonnes of REO per annum.
 
watchlist Created with Sketch. Add ARU (ASX) to my watchlist
(20min delay)
Last
19.5¢
Change
0.000(0.00%)
Mkt cap ! $450.5M
Open High Low Value Volume
19.5¢ 20.0¢ 19.0¢ $534.1K 2.745M

Buyers (Bids)

No. Vol. Price($)
24 631081 19.0¢
 

Sellers (Offers)

Price($) Vol. No.
19.5¢ 91095 2
View Market Depth
Last trade - 16.10pm 12/07/2024 (20 minute delay) ?
ARU (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.