Oh yeah! Someone will make some money, not us but. Offer only a quarter of the US$342M.
"A Definitive Feasibility Study (DFS) was completed in December 2019 and updated in July 2020, which confirmed the Project’s economic viability and robustness. The capital cost of construction totals US$91M and returns an NPV8% of US$342M
These studies demonstrate the low risk and low cost nature of the planned Stage 1 which aims to produce 730,000ounces of gold at an AISC of US$713/oz which will place it in the lowest cost quartile of producing mines."
- Forums
- ASX - By Stock
- BRV
- Ann: Cash Offer from Aura Minerals Inc. of A$0.36 per share
Ann: Cash Offer from Aura Minerals Inc. of A$0.36 per share, page-5
- There are more pages in this discussion • 44 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)