It looks like PGY has almost completed decommissioning at Cliff...

  1. 19,648 Posts.
    lightbulb Created with Sketch. 1115
    It looks like PGY has almost completed decommissioning at Cliff Head , partly paid for by TEG Aug - Oct and PGY 100% since then

    Wells Secured & Pipeline flushed of oil August to February 2025

    • Actions towards non-production successful with facility shut-in, stable and safe.

    • Directions 1 & 2 - ensure wells, facilities and pipeline secure, free of oil and risks reduced to ALARP • Completed, awaiting final acceptance and closure from NOPSEMA. •

    Directions 3 to 5 - ensure ongoing appropriate steps taken after cessation of production to reduce risk to workforce and environment. Integrity management until facility re-purpose (or removal) Other Operational Regulatory achievements •

    Revised Environment Plan covering Non-Production Phase accepted .

    Tick off from NOPSEMA must be very close.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
0.3¢
Change
0.000(0.00%)
Mkt cap ! $6.267M
Open High Low Value Volume
0.0¢ 0.0¢ 0.0¢ $0 0

Buyers (Bids)

No. Vol. Price($)
53 57395151 0.2¢
 

Sellers (Offers)

Price($) Vol. No.
0.3¢ 5039819 12
View Market Depth
Last trade - 16.21pm 29/07/2025 (20 minute delay) ?
TEG (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.