HIGHLIGHTS
• Commissioning is progressing well and as planned at the Jaurdi Gold Project
• The 6MW power station has been commissioned and is now supplying base load power to the mill
• Plant compressor has been installed and testing commenced
• Raw water and process water dam and associated infrastructure installed and commissioned with
3 bores providing process water to the raw water dam
• Process slurry pump gland water circuit has been installed
• Tailings line to the Black Cat Tailings Storage Facility has been constructed and is being tested
• Commissioning and production ramp up phase expected to continue through until
August/September 2019
• Full production expected to be reached in Q4 2019 for an initial target throughput of 500,000tpa
and circa 25,000 ounces of gold recovered per annum
• PFS Results indicate forecast Life of Mine (LOM) revenue of $208.5 million and surplus operating
cash flow of $98.4 million at a AUD$1,650 gold price (versus current spot price of > AU$2,000) with
circa $17 million of applicable Australian carried forward tax losses
- Forums
- ASX - By Stock
- BCN
- Ann: Commissioning Commences for Australia's Next Gold Producer
Ann: Commissioning Commences for Australia's Next Gold Producer, page-231
Featured News
Add BCN (ASX) to my watchlist
(20min delay)
|
|||||
Last
2.5¢ |
Change
-0.001(3.85%) |
Mkt cap ! $93.91M |
Open | High | Low | Value | Volume |
2.6¢ | 2.6¢ | 2.5¢ | $52.52K | 2.100M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 405003 | 2.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
2.6¢ | 1243722 | 4 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 405003 | 0.025 |
8 | 1333410 | 0.024 |
3 | 505869 | 0.023 |
2 | 1125000 | 0.022 |
3 | 299000 | 0.021 |
Price($) | Vol. | No. |
---|---|---|
0.026 | 1243722 | 4 |
0.027 | 927406 | 3 |
0.028 | 9807869 | 6 |
0.029 | 2780433 | 8 |
0.030 | 6343535 | 13 |
Last trade - 15.50pm 22/07/2024 (20 minute delay) ? |
Featured News
BCN (ASX) Chart |