    " HIGHLIGHTS
    • Commissioning is progressing well and as planned at the Jaurdi Gold Project
    • The 6MW power station has been commissioned and is now supplying base load power to the mill
    • Plant compressor has been installed and testing commenced
    • Raw water and process water dam and associated infrastructure installed and commissioned with
    3 bores providing process water to the raw water dam
    • Process slurry pump gland water circuit has been installed
    • Tailings line to the Black Cat Tailings Storage Facility has been constructed and is being tested
    • Commissioning and production ramp up phase expected to continue through until
    August/September 2019
    • Full production expected to be reached in Q4 2019 for an initial target throughput of 500,000tpa
    and circa 25,000 ounces of gold recovered per annum
    • PFS Results indicate forecast Life of Mine (LOM) revenue of $208.5 million and surplus operating
    cash flow of $98.4 million at a AUD$1,650 gold price (versus current spot price of > AU$2,000) with
    circa $17 million of applicable Australian carried forward tax losses
 
watchlist Created with Sketch. Add BCN (ASX) to my watchlist
(20min delay)
Last
2.3¢
Change
0.000(0.00%)
Mkt cap ! $86.40M
Open High Low Value Volume
2.4¢ 2.4¢ 2.3¢ $31.68K 1.334M

Buyers (Bids)

No. Vol. Price($)
3 1409802 2.3¢
 

Sellers (Offers)

Price($) Vol. No.
2.5¢ 2207463 7
View Market Depth
Last trade - 15.36pm 06/09/2024 (20 minute delay) ?
BCN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.