    It looks like funding approval is imminent:
    - Stage 1.5 annual capacity: 625,000 ton
    - phosphate rock target in CY 2024: 440,000 Ton
    - Once funding is complete, the Company intends to undertake a 9 month construction program to complete the Stage 1.5 program
    - To be to deliver 440,000 Ton in CY 2022 ( More than two thirds of stage 1.5 capacity), the 9 month construction program should be completed in March/Apri 2024
    - Given construction program is 9 months, they should start in Aug 2023

    Happy to get some feedback on the above analysis.

    Good luck to shareholder

    Regards,
    Sam
 