It looks like funding approval is imminent:
- Stage 1.5 annual capacity: 625,000 ton
- phosphate rock target in CY 2024: 440,000 Ton
- Once funding is complete, the Company intends to undertake a 9 month construction program to complete the Stage 1.5 program
- To be to deliver 440,000 Ton in CY 2022 ( More than two thirds of stage 1.5 capacity), the 9 month construction program should be completed in March/Apri 2024
- Given construction program is 9 months, they should start in Aug 2023
Happy to get some feedback on the above analysis.
Good luck to shareholder
Regards,
Sam
- Forums
- ASX - By Stock
- Ann: Company Update & Future Outlook
It looks like funding approval is imminent:- Stage 1.5 annual...
-
-
- There are more pages in this discussion • 75 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add CXM (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.7¢ |
Change
0.001(2.78%) |
Mkt cap ! $32.05M |
Open | High | Low | Value | Volume |
3.6¢ | 3.7¢ | 3.6¢ | $19.53K | 540.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 500000 | 3.6¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.8¢ | 130000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 500000 | 0.036 |
3 | 1120714 | 0.035 |
3 | 195000 | 0.034 |
2 | 70333 | 0.033 |
1 | 451613 | 0.031 |
Price($) | Vol. | No. |
---|---|---|
0.038 | 130000 | 1 |
0.040 | 468321 | 3 |
0.041 | 406733 | 3 |
0.042 | 23833 | 1 |
0.044 | 223896 | 2 |
Last trade - 14.36pm 18/10/2024 (20 minute delay) ? |
Featured News
CXM (ASX) Chart |