A40 0.00% 8.2¢ alita resources limited

Ann: Corporate and Operations Update, page-197

  1. 821 Posts.
    lightbulb Created with Sketch. 416
    Yep, thats one of my main concerns too. Lets assume we achieve upper end (or best case) production guidance of 40kt in Q3, its based off an allocated $42M in forcasted production costs. That's over $1,000per tonne cost of production. Last qtr we achieved a selling price of $1078AUD so just covering costs once royalty taken out etc...
    Then we've got the additional 15M outgoings for the rest of the quarter too.

    I think its this stat alone has triggered the sell off.

    Surely the market cant be that bothered with our cash position because a concession has to be made re our stockpile at the end of the Q2...

    This is why i was hoping for C&M until either:
    - spod market picks back up and we sell spod profitably again
    - JV is finalised and ready to go with decent volumes 10k p/m
    - 2nd / 3rd offtake binding, fines up and running, lowering production costs etc..

    Cant help but feel that keeping the plant operating at full tilt as proposed in the qtrly will do nothing much else other than deplete both our cash reserves and eating into our remaining LOM.
 
watchlist Created with Sketch. Add A40 (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.