A lot more flesh on the commissioning issues from the Shaw report
However, the commissioning process has not gone as smoothly, and the team have encountered a number of issues which has slowed the ramp-up including:
• Availability of the dozer mining units due to a range of electrical and mechanical failures.
• Reliability of the power infrastructure which caused a number of power outages.
• Issues with pump mechanical seals in the Wet Concentration Plant (WCP).
• The transition to in-pit disposal of sand tailings (from the off-path storage facility) has impacted mining activities due to capacity constraints caused by increased water mounding within the pit and additional infrastructure being required.
• Slower than expected commissioning and operation of the MSP.
Also any thoughts on Dozer mining vs truck & shovel for our style of operation?
Thanks
- Forums
- ASX - By Stock
- Ann: Corporate Presentation - Noosa Mining Investor Conference
Vince A lot more flesh on the commissioning issues from the Shaw...
- There are more pages in this discussion • 17 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add STA (ASX) to my watchlist
(20min delay)
|
|||||
Last
9.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $138.9M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
STA (ASX) Chart |
Day chart unavailable
The Watchlist
LU7
LITHIUM UNIVERSE LIMITED
Alex Hanly, CEO
Alex Hanly
CEO
SPONSORED BY The Market Online