Originally posted by sandfire:
↑
Here is a summary of John Downie's reply to my email regarding the CRC. Only $9.2m of the $20m for critical metals was allocated. The CRC review panel have been clear we are eligible to apply again, round 8 closes 24 sept. We will have ticked a number of boxes, the site in Townsville is confirmed the PFS will be completed. The CSIRO will have completed the next stage of their laboratory work on the refinery section of the plant. So we will have a very strong case for this round 8. The bulk sample will begin on the week of 2nd Sept (a little later than we had planned) However we will keep the project on track (with only minor slippage)
Expand
Thanks for the update mate. If only the company did it through asx and more frequently, that would help to make more clear investment decisions considering the volatility.