PAN 0.00% 3.5¢ panoramic resources limited

From qtry report; Pre-production and rehabilitation work in...

  1. 182 Posts.
    lightbulb Created with Sketch. 5
    From qtry report;
    Pre-production and rehabilitation work in October and November were on plan, however the production ramp up in
    December was slower than forecast due to a combination of factors, including:
    • Delays in recruiting various operational and maintenance roles;
    • Mobile equipment availability; and
    • A severe storm which required personnel to be deployed elsewhere to repair damage and to reinstate services.


    So we knew there had been issues, but this was nearly 2 months ago. Bit smelly. Bank wants a bigger piece of it
 