Hi Stirer,
No, the announcements stated Jinpeng needed to achieve 48 hours of continuous production and they expected this to be achieved in Several Weeks.
2nd of May 2024 ASX announcement.
It is expected to take several weeks to achieve the 48 hours of uninterrupted production at nameplate capacity to have the plant formally commissioned under the EPC Contract. Until that point the plant remains under the control and responsibility of the EPC contractor.
Can you provide the ASX announcement you refer to that confirms Jinpeng has completed commissioning and the plant has formally been handed over?
- Forums
- ASX - By Stock
- Ann: Development Progress - Lindi Jumbo Mine
Hi Stirer,No, the announcements stated Jinpeng needed to achieve...
Featured News
Add WKT (ASX) to my watchlist
(20min delay)
|
|||||
Last
9.2¢ |
Change
-0.004(4.17%) |
Mkt cap ! $61.75M |
Open | High | Low | Value | Volume |
9.7¢ | 9.7¢ | 8.9¢ | $45.75K | 501.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 200000 | 9.3¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
9.5¢ | 5315 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 200000 | 0.093 |
1 | 5500 | 0.092 |
1 | 10000 | 0.090 |
2 | 81246 | 0.089 |
2 | 58000 | 0.088 |
Price($) | Vol. | No. |
---|---|---|
0.095 | 5315 | 1 |
0.096 | 59293 | 2 |
0.098 | 61183 | 1 |
0.105 | 343296 | 3 |
0.110 | 169999 | 3 |
Last trade - 12.53pm 01/11/2024 (20 minute delay) ? |
Featured News
WKT (ASX) Chart |