Maclean also said in the December webinar after the assays are returned, and the MRE announced that they would "swiftly" move to the Camel Creek Scoping Study!
The Camel Creek MRE was released 8 March
You missed my point though, the company are suggesting that the plan to start drilling in November which is only 7 weeks away, and in that time they need to have Native Title clearance, a drilling permit issued and possibly a Heritage Survey completed.
Just as an example, another ASX listed company I follow has put back drilling by over 3 months as they wait on a Heritage Survey being completed but prior to that it was over 2 months of negotiations for a Native Title clearance.
@Money made indeed the Golden Cup results are due, but given the backlogs at the labs and the normal turn around period of 6 - 8 weeks for results / priorities at the lab, etc, it has been only 5 weeks since drilling was completed.
cheers