    EXCALIBUR MINING (ASX: EXM)
    www.excaliburmining.com.au

    ASX ANNOUNCEMENT - 10 March 2010
    Project Update: Juno Resource

    - Preliminary findings from independent review of Juno resource received
    - Downgrade of Juno indicated resource category anticipated
    - Downgrade does not impact Excalibur's other projects at Tennant Creek,
    including Up Dip Juno, M10 or the Nobles Nob Shallows
    - Drilling work at Juno is continuing and additional results are pending

    Excalibur Mining Corporation Limited (ASX: EXM) has an active program to advance its
    portfolio of Tennant Creek assets. This includes an ongoing drilling campaign and an
    external resource review, leading to a planned update to its resource position. The recent
    focus of the program has been a comprehensive analysis of the Juno resource estimate.

    At this stage, Excalibur does not have a new reportable resource position for Juno, but a
    substantial reduction in the indicated portion is anticipated.

    Based on the initial findings, the previous mining at Juno had a larger impact on Excalibur's
    resource than previously calculated. Excalibur's earlier resource estimates were based on
    an electronic data-base inherited from the Normandy Group.

    The preliminary findings of the Juno review and the resultant changes to drilling plans will
    delay the next resource statement from the previously planned March/April time frame.

    Excalibur Managing Director, Tim Lagdon said, "This does not change our conviction as to
    the quality of Excalibur's other Tennant Creek projects where, through our own drilling, we
    have demonstrated exceptional results".

    Background

    A core focus of the Company over the last 7 months has been to review the robustness of
    all of Excalibur's assets as a precursor to commencing a detailed feasibility process.

    This included Excalibur undertaking a rigorous program in relation to the Juno resource,
    which encompassed:

    Validation drilling to confirm stope locations, remnant pillars and drive locations;
    Verification of the resource database using the original hard-copy geological drilling logs
    and stope plans, which were recently located and acquired; and,
    An independent resources review by an external party.

    Cube Consulting ("Cube"), a respected specialist independent geo-scientific group, was
    engaged to work with Excalibur to undertake the resources review.
    ASX: EXM Press Release 10 March 2010


    Excalibur Mining Corporation Limited
    Excalibur Mining Corporation Limited
    Excalibur Mining Corporation Limited
    Excalibur Mining Corporation Limited



    ASX: EXM
    ASX: EXM
    ASX: EXM
    ASX: EXM


    ACN 008 021 118
    Ground Floor, 14 Outram Street, West Perth, WA 6005
    PO Box 1779, West Perth, WA 6872 | Tel +61 8 9322 8000 | Fax +61 8 9322 3005
    [email protected] | www.excaliburmining.com.au

    2
    22
    2



    The review identified a number of inaccuracies in the original electronic database, including
    errors in the stope models (which are critical for determining depletion from previous
    mining), spatial orientation and various typographical and transformation errors. A critical
    component has been the location of the ore body relative to survey points. As a direct
    consequence of information obtained earlier this year and the Juno verification drilling
    currently underway, the stopes have now been accurately positioned. With these changes,
    there is a much closer alignment of the modeled high grade ore and the previously mined
    stopes.

    The preliminary findings show that there is a poor reconciliation between the original
    electronic database and the new recreated database. The impact is that the previous Juno
    indicated resource was substantially overstated. While the magnitude of the overstatement
    is not yet known, Excalibur no longer has the requisite level of confidence in the previously
    reported Juno resource.

    The Board immediately sought a trading halt in Excalibur shares as soon as it became
    apparent that the review may result in a material downgrade of the Juno resource.

    Further work is required to determine the resource position at Juno. This will delay our
    planned resource update as we seek to reconcile the results and also incorporate the
    recent drilling; including an estimate of the mineralisation around the newly discovered Up-
    Dip portion of Juno when sufficient drilling results are available. The resource review will be
    expanded to cover the results from Excalibur's Juno drilling completed over the last 4
    months as these have not yet been incorporated.

    It should be noted that the anticipated resource downgrade relates specifically to the
    previous Juno indicated resource estimate. The inferred portion of the Juno resource has
    not yet been included in the resource analysis by Cube. Testing of these areas is in
    progress as part of the current drilling campaign. The change in resources at Juno will not
    impact the Up-dip portion of Juno where the recent drilling has been undertaken by
    Excalibur or in relation to M10 or around the Nobles Nob Shallows including Rising Sun,
    Weabers Find, Nobles Nob West and the newly discovered NM4 deposit.

    We will keep the market informed as results come to hand and will be reviewing Excalibur's
    strategy based on the findings. Additional results of drilling at Juno will be released to the
    ASX shortly.

    For further information, please contact:



    For further information, please contact:
    Tim Lagdon
    Managing Director
    Ph: +61 8 9322 8000

    Media enquiries:
    Fortbridge
    Ph: +61 2 9331 0655
    Luke Dean 0414 535 433
 
watchlist Created with Sketch. Add DSE (ASX) to my watchlist
(20min delay)
Last
$4.34
Change
-0.025(0.57%)
Mkt cap ! $305.6M
Open High Low Value Volume
$4.27 $4.35 $4.26 $72.75K 16.95K

Buyers (Bids)

No. Vol. Price($)
2 994 $4.33
 

Sellers (Offers)

Price($) Vol. No.
$4.35 2156 4
View Market Depth
Last trade - 12.36pm 14/11/2024 (20 minute delay) ?
DSE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.