The bridge/road upgrade is clearly on the critical path of the...

  1. 1,097 Posts.
    lightbulb Created with Sketch. 285
    The bridge/road upgrade is clearly on the critical path of the major construction works presumably required for the Dubbo plant. You can't have heavy vehicles going over a dodgy bridge or an old road, the infrastructure would get destroyed in no time or are not even legally allowed to be on. So earthworks, usually the first thing with any construction project, cannot even start as the machines and vehicles involved in earthworks are generally very heavy combined with the weight of the trucks they're transported on.

    This has to be done concurrently to any Dubbo design and approval works, or otherwise, if done in 'series' one after the other, as in if the design and approval and construction all come after FID of the Dubbo plant, then it will obviously be a several year delay to the Dubbo completion of construction.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
57.0¢
Change
-0.020(3.39%)
Mkt cap ! $115.3M
Open High Low Value Volume
59.0¢ 59.0¢ 57.0¢ $382.3K 660.0K

Buyers (Bids)

No. Vol. Price($)
7 54800 57.0¢
 

Sellers (Offers)

Price($) Vol. No.
57.5¢ 32829 3
View Market Depth
Last trade - 16.10pm 30/07/2025 (20 minute delay) ?
ASM (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.