Dear Andrew,
It has now been over 12 months since we secured the support from Premier Mark McGown and he personally requested the Department of Jobs, Tourism, Science and Innovation provide lead agency support to EGR to develop this project,
Not only have you missed the FID decision in early 2020, EGR is yet to secure a lease or any of the predevelopment activities that you stated in this ASX announcement,
How are we going to get into production in early 2021 without these significant milestones being completed?
With only 3 weeks left in the QTR, you are certainly leaving the lease and EPC contract to the last minute,
I think it is about time you picked up the phone and spoke to the Premier about getting this lease agreement signed, they are dealing with a state significant project.
It shouldn't take over 12 months to complete a lease agreement.
- Forums
- ASX - By Stock
- EGR
- Ann: EcoGraf development attracts WA Government support
Ann: EcoGraf development attracts WA Government support, page-28
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add EGR (ASX) to my watchlist
(20min delay)
|
|||||
Last
8.9¢ |
Change
0.000(0.00%) |
Mkt cap ! $40.40M |
Open | High | Low | Value | Volume |
8.9¢ | 8.9¢ | 8.9¢ | $346 | 3.888K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
4 | 82885 | 8.9¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
9.0¢ | 103331 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
4 | 82885 | 0.089 |
4 | 194090 | 0.088 |
1 | 11505 | 0.087 |
3 | 52000 | 0.086 |
1 | 10000 | 0.085 |
Price($) | Vol. | No. |
---|---|---|
0.090 | 103331 | 2 |
0.091 | 103204 | 1 |
0.092 | 39999 | 1 |
0.094 | 10000 | 1 |
0.095 | 58100 | 2 |
Last trade - 10.57am 09/10/2024 (20 minute delay) ? |
Featured News
EGR (ASX) Chart |
The Watchlist
AHK
ARK MINES LIMITED
Ben Emery, Executive Director
Ben Emery
Executive Director
SPONSORED BY The Market Online