    For those interested in Drill timing etc, see below the Transport Plan submitted (estimates for a single well) to estimate number of vehicle trips during drilling and production setup. Seems pretty quick - but I am no construction or drilling expert. But, I guess it gives an indication as to how quickly we could expect results.

    Excavation/Construction for drill pad: ~4 days
    Drilling (Rig Mobilising, Drilling, De-mob): ~8 days
    Pit Closure: ~6 days
    Production Equipment setup: ~16 days

    https://hotcopper.com.au/data/attachments/3538/3538198-ec184993c76490ba22ea49f6d9c3badc.jpg
    https://hotcopper.com.au/data/attachments/3538/3538200-b1e45c706127a5077caebf6861eebe0b.jpg

 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
0.5¢
Change
-0.001(9.09%)
Mkt cap ! $13.47M
Open High Low Value Volume
0.5¢ 0.6¢ 0.5¢ $45.15K 9.007M

Buyers (Bids)

No. Vol. Price($)
2 514861 0.5¢
 

Sellers (Offers)

Price($) Vol. No.
0.6¢ 3604481 9
View Market Depth
Last trade - 15.25pm 27/06/2025 (20 minute delay) ?
BNL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.